What is the solution?
After a full and comprehensive site survey has been carried out, D Evans Ltd proposes a schedule of remedial
action and upon acceptance, the affected roof area is thoroughly cleansed.
A four stage repair and maintenance system is then implemented:
- The area is rendered clean and dry
- A Sealant is gun-applied into the gap
- A Basecoat is brush-applied to all exposed steelwork
- A brushable Topcoat is applied
Continual Assessment
Ongoing Technical Assessments are carried out by the manufacturer to ensure all remedial work has complied with the specification. Every aspect of the project will be checked and the frequency of visits will depend upon the size and duration of the project.